The contractor is preparing for the final layer of asphalt to be installed on Central Avenue beginning Monday, April 29, 2024.

The proposed schedule is as follows: (weather dependent)

  • Monday – Milling or grinding down portions of Central Avenue
  • Tuesday & Wednesday – Final layer of asphalt and striping

If you have any questions, feel free to reach out to [email protected]. If you need immediate assistance, call the project hotline at 813-580-5313. 