Central Avenue – Final Layer of Asphalt
Dear Resident,
The contractor is preparing for the final layer of asphalt to be installed on Central Avenue beginning Monday, April 29, 2024.
The proposed schedule is as follows: (weather dependent)
- Monday – Milling or grinding down portions of Central Avenue
- Tuesday & Wednesday – Final layer of asphalt and striping
If you have any questions, feel free to reach out to [email protected]. If you need immediate assistance, call the project hotline at 813-580-5313.
Thanks for your patience as we work to improve the utilities in the Seminole Heights area.