Schedule Update – Aug. 2, 2022
City staff and members of the project team presented an update to the Old Seminole Heights Neighborhood Associations July 26, 2022. The project team explained that work is occurring in multiple locations at once in order to meet the City’s 40-month construction schedule; sequential construction would take 6-7 years to complete.
The project team also discussed the map graphic shown below and corresponding anticipated construction dates. Areas shown in purple are currently under construction. Work has recently started in the areas shown in orange, and work on Florida Avenue, shown in pink, is scheduled to begin Aug. 22. The dates shown below are subject to change due to inclement weather or other unforeseen conditions.