  • This is a photoshopped imaged to show conceptually what Crest Avenue will look like after construction. It will be repaved with asphalt and have new gutters and curbs.

Crest Avenue Construction

Construction on Crest Avenue will last 6-9 months. This duration is required because crews must install new sewer mains on both the north and south sides of Crest Avenue and connect homes to those new lines before removing the old sewer line in the center of the road. Crest Avenue will be closed to through traffic during construction. Driveway access will be limited at times, so the contractor will work with individual households to identify alternate parking, and if needed, provide alternate means of transporting residents to and from temporary parking. Services such as trash collection, recycling collection, mail and deliveries will continue without interruption.

Following are the steps involved in Crest Avenue Construction. Click on any thumbnail to enlarge the rendering.

This rendering depicts utilities to be installed under Crest Avenue, including two new sewer lines, a new water line and a new box culvert.

Install New South Sanitary Sewer

  • Install shallow wells to dewater south side of Crest Avenue. Pumps will run 24 hours a day, seven days a week prior to and during construction.
  • Remove asphalt and excavate south side of Crest Avenue and right-of-way.
  • Install new south sanitary sewer.
  • Connect homes on the south side of Crest to the new sewer line.
  • Backfill trench and place temporary gravel driving surface.
This rendering shows an excavated trench on the south side of Crest Avenue and a new sanitary sewer being installed

Install New North Sanitary Sewer

  • Install shallow wells to dewater north side of Crest Avenue. Pumps will run 24 hours a day, seven days a week prior to and during construction.
  • Remove asphalt and excavate north side of Crest Avenue and right-of-way.
  • Install new north sanitary sewer.
  • Connect homes on the north side of Crest to the new sewer line.
  • Backfill trench and place temporary gravel driving surface.
This rendering shows an excavated trench on the north side of Crest Avenue and a new sanitary sewer being installed

Install New Stormwater Box Culvert

  • Continue running dewatering pumps 24 hours a day, seven days a week on Crest Avenue.
  • Remove existing sanitary sewer line.
  • Install the new stormwater box culvert.
  • Backfill trench and place temporary gravel driving surface.
This rendering shows an excavated trench that is the full width of Crest Avenue and a new seven-foot by four-foot box culvert being installed.

Install New Drinking Water Line

  • Remove gravel and excavate north side of Crest Avenue and right-of-way. Continue running dewatering pumps 24 hours a day, seven days a week on Crest Avenue.
  • Install new drinking water line.
  • Backfill trench and restore Crest Avenue with new asphalt, gutters and curbs.
This rendering shows an excavated trench on the north side of Crest Avenue and a new drinking water line being installed.