West Crest Avenue Update

Crews continue to make progress on the 100 and 200 blocks of West Crest Avenue. Road base has been installed. Sanitary sewer video inspections and adjustments should be finalized by Jan. 18, after which crews will begin installing curbs. Once curbs are installed, crews will begin installing asphalt, which could begin late the week of Jan. 16, but likely will occur the week of Jan. 23.

At the intersection of Highland and West Crest, the City has requested a different location for the ADA-accessible sidewalk ramp, which requires a change in the curb inlet that was installed. A different curb inlet has been ordered. Once received, crews will modify the inlet under a single lane closure on Highland Avenue. Residents will be notified in advance of this work, which will likely occur this spring. Final restoration will occur once the ADA-accessible sidewalk is installed.